Calculator · Substrate

Self-leveling compound calculator

Tiles need a flat substrate. If the screed is wavy or has hollows, you level it with a self-leveling compound. How much to buy depends almost entirely on the average layer thickness.

TileWright calculator with material quantities in kg and bags

Quick answer

kg needed = area × average thickness in mm × usage per mm. Most compounds take 1.5 to 1.7 kg per m² and mm.

Example: 12 m² at an average of 5 mm and 1.6 kg per mm gives 96 kg, which is 4 bags of 25 kg.

Self-leveler calculator

Measuring the average thickness

Lay a long straightedge or level across the floor in several directions and measure the gap at the low spots. A line laser is faster: set up a grid about one metre apart, measure the distance to the laser line at each point and take the average.

Use the average thickness, not the deepest spot. Applying a 12 mm low spot to the whole room can easily double the amount you buy.

Usage per millimetre

The bag states usage, usually in kg per m² and mm. It depends on the density of the compound.

Thicknessat 1.6 kg/m² per mmfor 12 m²
3 mm4.8 kg/m²58 kg
5 mm8.0 kg/m²96 kg
10 mm16.0 kg/m²192 kg

Before you pour

  • Vacuum the substrate and prime it with the manufacturer's primer. Otherwise the screed pulls water out of the compound and it cracks.
  • Fit edge insulation strips along all walls.
  • Stay within the product's permitted thickness. Deep areas need a compound rated for thicker layers.
  • Use exactly the water quantity on the label. Too much water leaves a soft surface.

The bag also says when the floor is walkable and ready for tiling. The job-site timer in TileWright reminds you.

Materials and waiting times under control

TileWright calculates leveler, adhesive and tiles in one project and sends a notification when the floor is walkable. Fully offline.

Download on the App Store

Frequently asked questions

How much self-leveler do I need per m²?

At 1.6 kg per mm it is 4.8 kg per m² for 3 mm and 8 kg per m² for 5 mm.

How do I work out the layer thickness?

Measure the gap to a straightedge or laser line at several points and average them. Don't apply the deepest spot to the whole room.

Do I need to prime before leveling?

Yes. Without primer the substrate draws water out of the compound, which weakens the bond and can cause cracks.